A flight-grade 1U CubeSat kit a high-school class can build in a semester and launch on a shared rideshare for under €30k. Open hardware, open ground-station, and a curriculum that walks teenagers through the same process used by ESA.

Feasibility at a glance
PT localization
7/10
High
Most steps can be localised in Portugal.
Per unit
€2,400–€3,800 per kit
at 25-unit volume
Starter batch
25units
minimum viable run
To first batch
20weeks
6 phases, design to ship
Budget
€60K–€133K
all-in estimate
Bottom line
Picked based on the localization score (7/10) plus the dominant process (cnc machining). For an early build at this batch size, this gives you the best balance of cost, risk, and speed of iteration.
4 capabilities
Wakes up after deployment and waits ten minutes before powering on.
Charges itself from the sun whenever the panels see daylight.
Takes Earth photos and broadcasts them on a frequency students can decode.
Logs orbit health so the class can debug their own design after launch.
4 stations · build route
Mill the chassis
5-axis CNC out of 7075 — the dimensional tolerances are hard but well-documented.
Stuff the boards
Reflow oven for the SMT layers, hand-solder the connectors that astronauts can fix.
Vibe and bake
Two weeks at a partner test lab — vibe table, then thermal-vacuum chamber.
Integrate and seal
Final torque, kapton tape, and then the cube doesn't open again until orbit.
Mill the chassis
5-axis CNC out of 7075 — the dimensional tolerances are hard but well-documented.
Stuff the boards
Reflow oven for the SMT layers, hand-solder the connectors that astronauts can fix.
Vibe and bake
Two weeks at a partner test lab — vibe table, then thermal-vacuum chamber.
Integrate and seal
Final torque, kapton tape, and then the cube doesn't open again until orbit.
3 identified · 1 blocking
High
Single-source ICs become unobtainable
Modern designs almost always include one IC with ≥30 week lead times when demand spikes.
Mitigation — Pin the BOM to two qualified part numbers per critical line and place rolling forecast orders.
Medium
Firmware ships before it's stable
Hardware looks done, software is still landing fixes — early customers feel it.
Mitigation — Hold the launch ship-date on a single firmware-stability KPI, not on hardware readiness alone.
Medium
CE / FCC test fail on first attempt
Most first-time radios fail EMC; budget a re-spin.
Mitigation — Pre-scan in a partner anechoic chamber before the official lab visit.
20 weeks to first batch
CNC machining
wk 1–2Anodising
wk 3PCB fabrication
wk 4SMT pick-and-place
wk 5Soldering
wk 6Functional QA & batch sign-off
wk 7CNC machining
Anodising
wk 1–2 is the longest stretch — CNC machining takes 2 weeks of the 7 weeks on this build.
6 materials · 7 processes
Materials
Processes
586 Portuguese manufacturers matched
None cover the whole build — it splits across steps.
9 tasks · 30 weeks to first batch
Week 1
2 tasks
Lock the pilot scope to one variant
One material set, one feature set, one user persona. Anything else is roadmap, not pilot.
Shortlist three vendors per critical step
Use GETMILK Match to pull a ranked list across the top three processes — cnc_machining, anodizing, pcb_fabrication. Send the same RFQ to all three; do not customise per vendor yet.
Weeks 2–3
2 tasks
Freeze the design for the first 10 units
Move the active CAD set to a tagged release; any change after the freeze gets logged in the change-board.
Place first-article orders with two of the three vendors
waits on Vendor shortlist signed off
Order one of each critical part at full spec. Do not buy 100 — buy 1, inspect, learn, then buy 100.
Weeks 4–7
2 tasks
Run the integration pilot
waits on First articles delivered
Ten complete units assembled in-house. Track yield, defect modes, and cycle time on a shared dashboard.
Kick off compliance + certification
Engage a notified body for the relevant standards. Booking a slot now beats discovering a 12-week wait later.
Weeks 8–16
2 tasks
Put 25 units in the hands of lighthouse users
waits on Integration pilot complete
These users help refine the product, but they also become your first paid customers. Charge a symbolic price so the data is real.
Scale-readiness review with the chosen primary vendor
waits on Lighthouse trial telemetry
Before you tool up for 1000 units, walk the line together and agree on capacity, payment terms, and the failure-mode plan.
Ongoing
1 task
Stand up a customer support loop
Every defect that reaches a user becomes a ticket, a root cause, a fix, and a regression test on the line.
3 roles to fill before month one
EU electronics co-investment broker
Inova+
Knows the EIC funding gates intimately.
EMC test partner
ANACOM-listed test lab
Pre-scan saves you a re-spin on first official test.
Firmware contract studio
INESC TEC firmware group
Backstop for embedded headcount you can't yet hire.
3 things to avoid in this plan
watch-out
Founder time leaks into vendor management instead of customer development
certification
Compliance booked too late and blocks shipping for 8+ weeks
quality
Demand exceeds the chosen vendor's small-batch capacity right when momentum matters
2 tasks in week 1
Lock the pilot scope to one variant
PCB fabrication
SMT pick-and-place
Soldering
Functional QA & batch sign-off
586 matched · 8 shown, ranked by coverage
Covers, left to right: CNC Machining · Anodizing · PCB Fabrication · SMT Assembly · Soldering · Final Assembly · Testing & Inspection
Manufacturer
Location
Covers
Certifications
People
Portuguese producers per required step
Final Assembly
369
CNC Machining
212
Testing & Inspection
178
SMT Assembly
36
Soldering
13
PCB Fabrication
6
Anodizing
3
How many cover more than one step
The gap
Picked based on the localization score (7/10) plus the dominant process (cnc machining). For an early build at this batch size, this gives you the best balance of cost, risk, and speed of iteration.
Send one RFQ to the top 4
Keenfinity EMS, Uartrónica, Proto-Electronics, Exatronic — same package, one click.