A printable, surface-EMG controlled prosthetic hand designed to give amputees a dignified daily-driver for a fraction of the price of a clinical device. Open hardware, open firmware, and a builder community of teen makers.

Feasibility at a glance
PT localization
8/10
High
The whole build can be sourced in Portugal.
Per unit
€180–€280 per hand (BOM)
at 50-unit volume
Starter batch
50units
minimum viable run
To first batch
20weeks
6 phases, design to ship
Budget
€9K–€20K
all-in estimate
Bottom line
Picked based on the localization score (8/10) plus the dominant process (fdm printing). For an early build at this batch size, this gives you the best balance of cost, risk, and speed of iteration.
4 capabilities
Reads tiny electrical signals on the surface of the wearer's forearm.
Translates those signals into grip patterns — pinch, key-grip, wave, fist.
Drives five independent finger motors so the user can hold, point, or rest.
Logs grip-quality data so the user and their physiotherapist can tune the device together.
5 stations · build route
Print the shells
FDM PETG for strength, SLA resin for the knuckles where geometry is tight.
Assemble the drivetrain
Thread tendon cables through the knuckles, terminate on the servo horns.
Solder the EMG boards
SMT reflow for the analog front-end; the rest is hand-pluggable.
Calibrate to the wearer
30-minute session: the firmware learns the user's specific muscle pattern.
Hand-tune the grips
Adjust spring tension on each finger so a glass and an egg are both safe.
Print the shells
FDM PETG for strength, SLA resin for the knuckles where geometry is tight.
Assemble the drivetrain
Thread tendon cables through the knuckles, terminate on the servo horns.
Solder the EMG boards
SMT reflow for the analog front-end; the rest is hand-pluggable.
Calibrate to the wearer
30-minute session: the firmware learns the user's specific muscle pattern.
Hand-tune the grips
Adjust spring tension on each finger so a glass and an egg are both safe.
3 identified · 1 blocking
High
Single-source ICs become unobtainable
Modern designs almost always include one IC with ≥30 week lead times when demand spikes.
Mitigation — Pin the BOM to two qualified part numbers per critical line and place rolling forecast orders.
Medium
Firmware ships before it's stable
Hardware looks done, software is still landing fixes — early customers feel it.
Mitigation — Hold the launch ship-date on a single firmware-stability KPI, not on hardware readiness alone.
Medium
CE / FCC test fail on first attempt
Most first-time radios fail EMC; budget a re-spin.
Mitigation — Pre-scan in a partner anechoic chamber before the official lab visit.
20 weeks to first batch
FDM 3D printing
wk 1–2SLA 3D printing
wk 3PCB fabrication
wk 4SMT pick-and-place
wk 5Wire-harness build
wk 6Functional QA & batch sign-off
wk 7FDM 3D printing
SLA 3D printing
PCB fabrication
SMT pick-and-place
Wire-harness build
Functional QA & batch sign-off
wk 1–2 is the longest stretch — FDM 3D printing takes 2 weeks of the 7 weeks on this build.
6 materials · 7 processes
Materials
Processes
5 principles
A myoelectric hand has to be light, quiet and reliable while turning noisy muscle signals into grips the wearer trusts. Weight at the end of the arm, signal quality and finger durability decide whether people keep wearing it.
1
Keep mass close to the wrist
Every gram at the fingertips feels heavier on a residual limb. Put motors, battery and board near the socket and route tendons out to the fingers.
2
Treat EMG quality as a mechanical problem
Electrode contact pressure, sweat and socket fit cause most signal loss. Design the electrode mount and shielding with the socket, not after it.
3
Make fingers fail safe and back-drivable
A finger should open under overload instead of breaking or crushing. Compliant joints and torque limits protect both the user and the gear train.
4
Plan for medical device rules early
A prosthesis sold in the EU falls under the Medical Device Regulation (EU 2017/745). Risk management to ISO 14971 and electrical safety to IEC 60601-1 shape design choices.
5
Design tendons for easy replacement
Cables stretch and fray. Accessible anchors and standard crimps let a technician swap one in minutes.
Common pitfalls
Avoid
Testing grips only on the bench and not on a real socket with sweat and movement.
Avoid
Choosing printed parts without checking fatigue and creep under constant tendon load.
Avoid
Leaving battery placement and heat to the end, then finding the socket too heavy or warm.
Avoid
Assuming an open-source design avoids medical device obligations when it is sold or fitted.
4 phases
Affordable bionic hands are moving from hobby projects towards fitted clinical devices. The points below are trends, not forecasts.
2026–2028
Better signal processing
Trend: pattern recognition on small microcontrollers replaces simple two-electrode open and close control.
2028–2031
Sensory feedback
Trend: vibration or pressure feedback tells the wearer how hard they are gripping.
2031–2034
Clinic-led customisation
Trend: 3D scanning and printing of sockets and shells becomes routine in fitting clinics.
2034–2036
Longer life and repair networks
Trend: modular parts and local repair reduce downtime and total cost of ownership.
Outlook
Expect lower-cost hands to compete on fit, reliability and clinical support more than on finger count.
8 materials
PETG
Low supply risk
Printed shell and brackets
Sourced from: Made from PET resins produced in the EU, US and Asia; filament widely available.
TPU 95A
Low supply risk
Flexible joint pads
Sourced from: Thermoplastic polyurethane is produced in Europe, the US and China.
Stainless steel
Low supply risk
Tendon cables and crimps
Sourced from: Produced widely in the EU and Asia; China is the largest producer.
FR-4 PCB laminate
Medium supply risk
Circuit boards
Sourced from: Most laminate and board production is in China and Taiwan; smaller European board makers exist.
Lithium-ion / lithium-polymer cells
High supply risk
Battery pack
Sourced from: Cell production is dominated by China, South Korea and Japan; EU cell capacity is growing but limited.
Shipping follows UN 38.3; EU battery rules add labelling and recycling duties.
Silicone elastomer
Low supply risk
Fingertip pads
Sourced from: Made from silicon metal and methyl chloride; large producers in China, the US and the EU.
Copper
Medium supply risk
Wiring, motor windings and traces
Sourced from: Mined mainly in Chile, Peru and DR Congo; Portugal mines copper at Neves-Corvo.
NdFeB magnets
High supply risk
Inside the small finger gear motors
Sourced from: China dominates rare earth processing and magnet output.
Usually bought inside complete gear motors.
5 companies from the atlas
Aveiro
PCB design, fabrication and SMT assembly
Mainboard and EMG sensor boards.
Braga
Prototype PCB fabrication and assembly
Quick-turn EMG sensor board revisions.
Oeiras
SLA and FDM printing
Fine SLA knuckle brackets and FDM PETG shell parts.
Porto
FDM printing and engineering R&D
Shell and bracket iteration and fatigue checks.
Vila Nova de Paiva
Wire harness production
Internal harness from battery to motors and sensors.
482 Portuguese manufacturers matched
None cover the whole build — it splits across steps.
482 matched · 8 shown, ranked by coverage
Services each manufacturer can handle for this build.
Manufacturer
Location
Covers
Certifications
People
Aveiro, NUTS2 PT16
ISO 13485, ISO 27001
28
Aveiro
ISO 9001, ISO 14001, ISO 27001, ISO 45001, IATF 16949, IPC-A-610, RoHS Compliance
—
Portuguese producers per required step
Final Assembly
369
Testing & Inspection
178
SMT Assembly
36
FDM 3D Printing
33
PCB Fabrication
6
Wire Harness
5
SLA 3D Printing
1
How many cover more than one step
The gap
Picked based on the localization score (8/10) plus the dominant process (fdm printing). For an early build at this batch size, this gives you the best balance of cost, risk, and speed of iteration.
Send one RFQ to the top 4
Exatronic, Keenfinity EMS, Uartrónica, Sogeclair Aerospace — same package, one click.
9 tasks · 30 weeks to first batch
Week 1
2 tasks
Lock the pilot scope to one variant
One material set, one feature set, one user persona. Anything else is roadmap, not pilot.
Shortlist three vendors per critical step
Use GETMILK Match to pull a ranked list across the top three processes — fdm_printing, sla_printing, pcb_fabrication. Send the same RFQ to all three; do not customise per vendor yet.
Weeks 2–3
2 tasks
Freeze the design for the first 10 units
Move the active CAD set to a tagged release; any change after the freeze gets logged in the change-board.
Place first-article orders with two of the three vendors
waits on Vendor shortlist signed off
Order one of each critical part at full spec. Do not buy 100 — buy 1, inspect, learn, then buy 100.
Weeks 4–7
2 tasks
Run the integration pilot
waits on First articles delivered
Ten complete units assembled in-house. Track yield, defect modes, and cycle time on a shared dashboard.
Kick off compliance + certification
Engage a notified body for the relevant standards. Booking a slot now beats discovering a 12-week wait later.
Weeks 8–16
2 tasks
Put 25 units in the hands of lighthouse users
waits on Integration pilot complete
These users help refine the product, but they also become your first paid customers. Charge a symbolic price so the data is real.
Scale-readiness review with the chosen primary vendor
waits on Lighthouse trial telemetry
Before you tool up for 1000 units, walk the line together and agree on capacity, payment terms, and the failure-mode plan.
Ongoing
1 task
Stand up a customer support loop
Every defect that reaches a user becomes a ticket, a root cause, a fix, and a regression test on the line.
3 roles to fill before month one
EU electronics co-investment broker
Inova+
Knows the EIC funding gates intimately.
EMC test partner
ANACOM-listed test lab
Pre-scan saves you a re-spin on first official test.
Firmware contract studio
INESC TEC firmware group
Backstop for embedded headcount you can't yet hire.
3 things to avoid in this plan
cost
Founder time leaks into vendor management instead of customer development
certification
Compliance booked too late and blocks shipping for 8+ weeks
quality
Demand exceeds the chosen vendor's small-batch capacity right when momentum matters
2 tasks in week 1
Lock the pilot scope to one variant