A pair of soft haptic gloves that mirror each other in real time. Squeeze one and your grandmother across the country feels the same gentle pressure on her palm. Designed for caregivers, partners, and grieving families.

Feasibility at a glance
PT localization
8/10
High
The whole build can be sourced in Portugal.
Per unit
€140–€220 per pair
at 200-unit volume
Starter batch
200units
minimum viable run
To first batch
6 phases, design to ship
Budget
€28K–€62K
all-in estimate
Bottom line
Picked based on the localization score (8/10) plus the dominant process (smt assembly). For an early build at this batch size, this gives you the best balance of cost, risk, and speed of iteration.
4 capabilities
Reads the wearer's grip pressure across a soft sensor woven into the palm.
Sends an encrypted pressure pattern to the paired glove anywhere on Earth.
Inflates micro air bladders in the receiving glove to recreate the squeeze.
Logs only the timing of the touches — never the pressure data — for memory keepsakes.
3 stations · build route
Knit the shells
Industrial flat-bed knitting, conductive yarn on the palm grid only.
Build the wrist module
Tiny 4-layer PCB, micro-pump and 250 mAh cell in a TPU housing.
Pair, test, ship
Each pair is paired and burned-in for 24 hours before it ever leaves the workshop.
Knit the shells
Industrial flat-bed knitting, conductive yarn on the palm grid only.
Build the wrist module
Tiny 4-layer PCB, micro-pump and 250 mAh cell in a TPU housing.
Pair, test, ship
Each pair is paired and burned-in for 24 hours before it ever leaves the workshop.
3 identified · 1 blocking
High
Single-source ICs become unobtainable
Modern designs almost always include one IC with ≥30 week lead times when demand spikes.
Mitigation — Pin the BOM to two qualified part numbers per critical line and place rolling forecast orders.
Medium
Firmware ships before it's stable
Hardware looks done, software is still landing fixes — early customers feel it.
Mitigation — Hold the launch ship-date on a single firmware-stability KPI, not on hardware readiness alone.
Medium
CE / FCC test fail on first attempt
Most first-time radios fail EMC; budget a re-spin.
Mitigation — Pre-scan in a partner anechoic chamber before the official lab visit.
12 weeks to first batch
SMT pick-and-place
wk 1–2PCB fabrication
wk 3Soldering
wk 4Wire-harness build
wk 5Cable assembly
wk 6Functional QA & batch sign-off
wk 7SMT pick-and-place
PCB fabrication
wk 1–2 is the longest stretch — SMT pick-and-place takes 2 weeks of the 7 weeks on this build.
6 materials · 7 processes
Materials
Processes
414 Portuguese manufacturers matched
None cover the whole build — it splits across steps.
9 tasks · 22 weeks to first batch
Week 1
2 tasks
Lock the pilot scope to one variant
One material set, one feature set, one user persona. Anything else is roadmap, not pilot.
Shortlist three vendors per critical step
Use GETMILK Match to pull a ranked list across the top three processes — smt_assembly, pcb_fabrication, soldering. Send the same RFQ to all three; do not customise per vendor yet.
Weeks 2–3
2 tasks
Freeze the design for the first 10 units
Move the active CAD set to a tagged release; any change after the freeze gets logged in the change-board.
Place first-article orders with two of the three vendors
waits on Vendor shortlist signed off
Order one of each critical part at full spec. Do not buy 100 — buy 1, inspect, learn, then buy 100.
Weeks 4–7
2 tasks
Run the integration pilot
waits on First articles delivered
Ten complete units assembled in-house. Track yield, defect modes, and cycle time on a shared dashboard.
Kick off compliance + certification
Engage a notified body for the relevant standards. Booking a slot now beats discovering a 12-week wait later.
Weeks 8–16
2 tasks
Put 25 units in the hands of lighthouse users
waits on Integration pilot complete
These users help refine the product, but they also become your first paid customers. Charge a symbolic price so the data is real.
Scale-readiness review with the chosen primary vendor
waits on Lighthouse trial telemetry
Before you tool up for 1000 units, walk the line together and agree on capacity, payment terms, and the failure-mode plan.
Ongoing
1 task
Stand up a customer support loop
Every defect that reaches a user becomes a ticket, a root cause, a fix, and a regression test on the line.
3 roles to fill before month one
EU electronics co-investment broker
Inova+
Knows the EIC funding gates intimately.
EMC test partner
ANACOM-listed test lab
Pre-scan saves you a re-spin on first official test.
Firmware contract studio
INESC TEC firmware group
Backstop for embedded headcount you can't yet hire.
3 things to avoid in this plan
watch-out
Founder time leaks into vendor management instead of customer development
certification
Compliance booked too late and blocks shipping for 8+ weeks
quality
Demand exceeds the chosen vendor's small-batch capacity right when momentum matters
2 tasks in week 1
Lock the pilot scope to one variant
Soldering
Wire-harness build
Cable assembly
Functional QA & batch sign-off
414 matched · 8 shown, ranked by coverage
Covers, left to right: SMT Assembly · PCB Fabrication · Soldering · Wire Harness · Cable Assembly · Final Assembly · Packaging
Manufacturer
Location
Covers
Certifications
People
—
—
—
Porto, NUTS2 PT11
—
—
Portuguese producers per required step
Final Assembly
369
SMT Assembly
36
Soldering
13
Cable Assembly
12
PCB Fabrication
6
Wire Harness
5
Packaging
0
How many cover more than one step
The gap
Picked based on the localization score (8/10) plus the dominant process (smt assembly). For an early build at this batch size, this gives you the best balance of cost, risk, and speed of iteration.
Send one RFQ to the top 4
Keenfinity EMS, Uartrónica, Proto-Electronics, ACEMIS France — same package, one click.